AI data centers turn to retired jet engines for faster power
Facing multi-year waits for grid power, some AI data centers are generating their own electricity with converted jet engines, the New York Times reported.
Grid queues and turbine shortages are pushing some AI data center operators toward an unlikely power source: jet engines pulled from retired aircraft and rebuilt to burn natural gas, according to a New York Times report. The appeal isn’t permanence — these aren’t anyone’s idea of a lasting power plant — but speed. Rystad Energy analyst Audun Martinsen told the Times that jet-powered units can have a data center running in about 24 months, calling it “all about getting power as fast as possible.” By contrast, connecting 100 megawatts to the grid in Northern Virginia takes roughly seven years, per the International Energy Agency, and a Mitsubishi Power executive told Bloomberg that most new power capacity isn’t expected until 2031.
The delays are already costing deals. Last month, Microsoft withdrew as anchor tenant for Nscale’s planned data center in Loughton, England, once the regional utility there warned it would be unable to deliver sufficient capacity before the early-to-mid 2030s. Elon Musk’s xAI has gone a different route: satellite images and state permitting records examined by the Times show the company fitted eight repurposed jet turbines in Mississippi to power its Colossus 2 facility in Memphis; the hardware is supplied by ProEnergy, a firm that overhauls GE jet engines pulled from retired Boeing airliners. OpenAI took a similar path in 2025, running gas turbines at its first Stargate campus in Abilene, Texas, where builder Crusoe placed an order for 13 more converted ProEnergy units this past April. Crusoe later backed out of a separate, $1.25 billion purchase of 29 gas turbines from Boom Supersonic — a company better known for building a supersonic passenger jet, now also marketing a turbine version of that jet’s engine as backup power for data centers — though a company spokesperson told TechCrunch that Crusoe intends to keep using turbines regardless.
The Trump administration is separately encouraging data centers to generate their own power, adding to the pressure. But converted jet engines carry trade-offs: they’re less efficient and pollute more than purpose-built gas turbines, and more of them are needed to produce the same output, the Times reported — which some experts think could make the approach a short-term play as efficiency and environmental concerns grow more pressing within a year or two.
Why it matters
The scramble for jet-engine power is a concrete symptom of how far electricity supply has fallen behind AI infrastructure buildout — and a sign that power access, not chip supply, is becoming the binding constraint on how quickly data center operators can bring new capacity online.